Planning a Feed Mill Shutdown: A 6-Week Checklist

9 minutes ago
2 min read

A planned shutdown is the best chance all year to fix what's wearing out before it fails. It's also easy to waste. Parts that don't arrive, jobs that weren't scoped and a rushed restart can turn a planned outage into an unplanned one.


Here's a week-by-week checklist to keep your next shutdown on track.


Feed mill shutdown 6-week planning checklist

6 Weeks Out: Set the Scope

  • List every job you want done, from hammer mills and dryers to conveyors, bearings and electrical.

  • Pull maintenance records to see what's due and what's failed since the last outage.

  • Walk the plant with operators. They know which noises, leaks and vibrations have been getting worse.

  • Rank jobs by risk: what could stop production if it isn't done now?


5 Weeks Out: Order Parts

  • Order wear parts and long-lead items now. Hammers, screens, liners, bearings, airlock parts and seals.

  • Confirm dimensions against what's installed, not just part numbers on file.

  • Order complete, weight-matched hammer sets for each mill. See hammer mill rotor balance.

  • Add critical spares you'll keep after the shutdown. See the hammer mill parts that wear out first.


4 Weeks Out: Line Up People

  • Confirm in-house crews and assign each job an owner.

  • Book contractors for specialized work like welding, electrical or rotor balancing.

  • Plan the sequence so crews aren't waiting on each other.


3 Weeks Out: Safety and Permits

  • Review lockout/tagout for every piece of equipment.

  • Plan confined space, hot work and lifting permits.

  • Confirm PPE and equipment: lifts, rigging, lighting and ventilation.


2 Weeks Out: Confirm and Stage

  • Confirm every part has shipped, with tracking.

  • Stage tools and parts near each job.

  • Prepare inspection sheets so crews record what they find. Our shutdown inspection checklist covers the hammer mill wear system.


1 Week Out: Final Check

  • Hold a pre-shutdown meeting to review jobs, sequence, safety and the restart plan.

  • Run inventory down to make cleanout faster.

  • Check that every part is on site. Not ordered, not shipped: on site.


During the Shutdown

  • Inspect before you replace, and record what you find with photos and measurements.

  • Check rods, pins and spacers when hammers come off.

  • Look for uneven screen wear, which can point to feed or chamber problems. See hammer mill screen utilization.


Restart and Follow-Up

  • Restart in steps and watch amps, vibration and temperature.

  • Check particle size on each mill after restart.

  • Write down what you learned: parts used, surprises and what to order for next time.


Frequently Asked Questions

How far ahead should a feed mill shutdown be planned?


At least six weeks for a typical planned shutdown, and earlier if you need long-lead parts or outside contractors.


What parts should be ordered before a shutdown?


Hammers, screens, liners, rods, bearings, seals and any other wear parts due for replacement, plus critical spares to keep on hand.


What's the most common shutdown mistake?


Parts that aren't on site when the work starts. Confirm delivery, not just the order.


What should be checked after restart?


Motor amps, vibration, temperature and particle size on each mill, so problems show up early.